It is recommended that the Director gives permission to procure a contractor to undertake the full roof replacement (plus potential internal works) to Jericho Primary School
Decision type: Key
Reason Key: Combined;
Decision status: For Determination
Wards affected: Hillcrest and Hensingham;
Notice of proposed decision first published: 04/03/2025
Anticipated restriction: Public -
OSCtte: People Overview and Scrutiny Committee;
Decision due: Between 4 Apr 2025 and 1 May 2025 by Director of Business Transformation and Change
Lead member: Portfolio Holder - Financial Planning and Assets
Lead director: Director of Business Transformation and Change
Contact: Matthew Hornsby, Project Lead Email: Matthew.Hornsby@cumberland.gov.uk Email: matthew.hornsby@cumberland.gov.uk.
Consultees
Consultation has taken place with the following groups:
• Jericho Primary School – Senior Management Team
• Education Capital Programme Group
This has been by a mix of meetings, letters, surveys and 1 - 2 - 1’s. This consultation format will continue for the duration of the project.