Issue details

Award of Stage 2 (Construction) of a Design and Build contract for the Port of Workington Roads project

To award Stage 2 of a D&B contract to Thomas Armstrong Ltd in order to deliver a heavy-duty road at the Port of Workington.

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: For Determination

Wards affected: Seaton;

Notice of proposed decision first published: 28/06/2024

Anticipated restriction: Public  -

OSCtte: Business and Resources Overview and Scrutiny Committee;

Decision due: Between 1 Aug 2024 and 31 Aug 2024 by Portfolio Holder - Financial Planning and Assets

Lead member: Portfolio Holder - Financial Planning and Assets

Lead director: Director of Business Transformation and Change

Contact: Ged Acton, Programme Manager Email: ged.acton@cumberland.gov.uk Email: ged.acton@cumberland.gov.uk.

Consultees

No further consultation is planned